win 2a7b731484 feat(finance): implement Phase 1 core P&L service + wire into dashboard
- Add internal/service/finance/types.go: AssetType enum, param/result structs
- Add internal/service/finance/service.go: Service interface, read-only ctor
- Add internal/service/finance/query_user.go: QueryUserProfitLoss (4 fan-out scans)
- Add internal/service/finance/query_activity.go: QueryActivityProfitLoss (4 fan-out scans)
- Add internal/service/finance/service_test.go: 22 integration tests (all pass)
- Wire finance.Service into admin handler (admin.go)
- Replace dashboard_activity cost scan with finance.Service call (D-09: value_cents single source of truth)
- Revenue/gamepass/draw-count scans unchanged; response schema fully compatible

Co-Authored-By: claude-flow <ruv@ruv.net>
2026-03-21 18:38:33 +08:00

64 lines
1.9 KiB
Markdown

# Project State
## Project Reference
See: .planning/PROJECT.md (updated 2026-03-21)
**Core value:** 提供可复用的盈亏统计方法,使平台运营能从用户和活动两个维度快速了解各类资产的收支状况
**Current focus:** Phase 2 — Per-Asset-Type Breakdown
## Current Position
Phase: 1 of 2 (COMPLETE) → Phase 2 next
Plan: 4/4 in Phase 1 complete
Status: Phase 1 complete — ready to plan Phase 2
Last activity: 2026-03-21 — Phase 1 executed: QueryUserProfitLoss + QueryActivityProfitLoss implemented, 22 tests passing
Progress: [█████░░░░░] 50%
## Performance Metrics
**Velocity:**
- Total plans completed: 0
- Average duration: — min
- Total execution time: 0 hours
**By Phase:**
| Phase | Plans | Total | Avg/Plan |
|-------|-------|-------|----------|
| - | - | - | - |
**Recent Trend:**
- Last 5 plans: —
- Trend: —
*Updated after each plan completion*
## Accumulated Context
### Decisions
Decisions are logged in PROJECT.md Key Decisions table.
Recent decisions affecting current work:
- Init: Fan-out + in-memory merge query pattern chosen (avoids Cartesian product JOINs)
- Init: Read-only DB routing enforced — constructor injects DbR only, no GetDbW() in package
- Init: All existing finance.* utilities (IsGamePassOrder, ComputeProfit, etc.) must be reused, not re-derived
- Init: Phase 2 (Fragment breakdown) requires schema verification of fragment_synthesis_logs join path before implementation
### Pending Todos
None yet.
### Blockers/Concerns
- Phase 2: fragment_synthesis_logs join path and cost formula not yet verified — requires schema review during Phase 2 planning
- Phase 1: SQLite test compatibility for CAST(AS SIGNED), GREATEST(), LIKE 'GP%' — must use Go-layer helpers or conditional SQL paths in integration tests
## Session Continuity
Last session: 2026-03-21
Stopped at: Roadmap created — ROADMAP.md and STATE.md written, REQUIREMENTS.md traceability updated
Resume file: None